Client & Project

Agip
Toni Project


Project Type

Manifolds


Field Overview

Toni is a tie back to Tiffany field located in block 16/17
(P 225).                    

Partners; Agip, Fina, Burlington Resources and Murphy Petroleum.

Toni holds  50 million bbl of oil, 1.55 bcm of gas.
First oil was achieved in December 1993.


Operator/Owner

Agip UK Limited


Contractor

McNulty Offshore Construction Limited


Work Locations

McNulty Quay, South Shields


Contract Duration

December 1990 – Mar 1992


Scope of Work

Supply, fabricate, fit out and commission subsea production and water injection manifolds including the fabrication and installation of Duplex pipework.