Client & Project
Nexen Petroleum UK Ltd
Ettrick Project
Project Type
Manifolds, SSIV, Mid Water Arch
Field Overview
Ettrick field is located on Blocks 20/2a and 20/3a in the UKCS.
Co-ventures include Nexen, Bow Valley Energy Ltd, Atlantic Petroleum.
Production planned the first quarter of 2008 using FPSO Aoka Mizu F. Peak production from the field is expected to be approximately 20,000 barrels of oil per day.
Operator/Owner
Nexen Petroleum UK Limited
Contractor
McNulty Offshore Construction Limited
Work Locations
McNulty Quay, South Shields
Contract Duration
December 2006 – August 2007
Scope of Work
Fabricate 700te of structures and pipework as follows:
- Mid water arch and clump weights,
- EDC Manifold and piles
- PLEM tie in structure and piles
- Riser bases
- Gas export SSIV structure