Client & Project
Wood Group
Piper Bravo
Project Type
Inlet Heater
Field Overview
Piper field is located on block 15/17 (P.220) in the UKCS.
Partners: Talisman, Transworld Petroleum, Lasmo. Interpid Energy
Production initially started on Piper Alpha in January 1973 with the replacement Bravo platform restarting production in 1993.
Oil reserves are 144 million tonnes (recoverable)
Operator/Owner
Talisman Energy
Contractor
McNulty Offshore Construction Limited
Work Locations
McNulty Quay, South Shields
Contract Duration
October 2006 – December 2006
Scope of Work
Fabricate Inlet Heater Module 6.5mt x 3.5 mt x 3.7 mt weight 25te
Management, Construction Engineering, Procurement (part), Fabrication, Mechanical Completion (inc. offshore pre-installed structures and pipe spools).
Installation of free issue Inlet Heater, junction boxes and associated cabling.
Piping hydrotesting and Nitrogen blanket preservation.