Client & Project

Texaco
Erskine Project


Project Type

Process Module


Field Overview

Located in block 23/26b in the UKCS sector of North Sea

Partners: Texaco, BP

Production commenced December 1997

Oil reserves 10 million tonnes and 10 billion cubic meters gas (recoverable).

HP/HT Field.


Operator/Owner

Texaco


Contractor

McNulty were part of an EPIC Integrated team


Work Locations

McNulty Quay, South Shields


Contract Duration

June 1995 – April 1997


Scope of Work

Integration Management, Construction Engineering, Procurement, Fabrication, Mechanical Completion of 1,500te Process Module (EPM) which included associated equipment and pipework.

  • SGS 9001:2001
  • SGS 14001:2004
  • SGS 18001:2007
  • 50th Anniversary British Safety Council
  • DNV
  • First Point Assessment
  • Achilles
  • Verify