Client & Project

Technip
East Area Field Development


Project Type

Integrated Deck


Field Overview

Development is located in blocks OML 67 and 70 offshore waters in Nigeria.

Partners: MPN and NNPC

Production started July 2006.

Oil reserves 530 million boe (recoverable)


Operator/Owner

MPN (Mobil Producing Nigeria)


Contractor

Joint Venture between:
McNulty Offshore Construction Limited And Consafe Engineering Services Ltd


Work Locations

Aberdeen, and McNulty Quay, South Shields


Contract Duration

Sep 2003 – Mar 2005


Scope of Work

Fabricate, fit out, load out and sea fasten 4,000te topsides which included Cellar and Main decks.