Owners and Project
Amerada Hess (UK) Limited
Rob Roy / Ivanhoe Development Project
Project Type
FPSO
Vessel Specification
Dimensions:
L82m, B75m, H30m, Accommodation: 100 persons
Capacity:
Oil 60,000 bopd,
Produced Water 45,000 bwpd, Water Injection 92,000 bwpd, Gas 58 mmscfd
Engineering
Brown & Root
Fabrication & Integration
McNulty Offshore Construction Limited
Work Locations
McNulty Quay, South Shields
Contract Duration
Aug 1987 – Apr 1989
Scope of Work
Management integration, Procurement, Construction Engineering, Fabrication, Installation, Commissioning assistance and Offshore Hook Up.
Removed and decanted and/or decommissioned 3,000te of redundant equipment, materials and liquids.
Install 12,000te of new topside equipment packages, pumps and other associated structures including flare and modifications to pontoons and strengthening of decks and columns.