Client & Project
Hess Corporation
Scott Field Development
Project Type
Process Module
Field Overview
Scott field is located on block 15/21a (P.218) in the UKCS.
Partners: Hess, Veba Oil, Kerr McGee. Premier
Production started on Scott in September 1993.
Oil reserves 59 million tonnes (recoverable)
Operator/Owner
Hess Corporation
Contractor
McNulty Offshore Construction Limited
Work Locations
McNulty Quay, South Shields
Contract Duration
Nov 1991 – Aug 1992
Scope of Work
Management, Construction Engineering, Procurement (part), Fabrication, Outfitting and Mechanical Completion of 1,000te Gas Treatment Module.